CoreGrid Engineering

Discipline · detailed engineering

Electrical Design & Engineering

AIS/GIS substation electrical engineering up to 765 kV, applied also to renewable pooling substations, solar and wind plants, BESS connections and the AC side of HVDC stations. Drawings, design calculations, studies and schedules are kept apart, as a design package keeps them.

Generic switchyard arrangement plan with five bays, transformer and control building
Generic illustration of a switchyard arrangement plan.

Scope and design basis

Electrical detailed engineering is the stage at which a tender or basic design becomes drawings and calculations that suppliers and site teams can build from. CoreGrid prepares it for AC voltages up to 765 kV, whether the work is a greenfield switchyard, a pooling substation for a renewable plant, a BESS connection or an extension to an existing station, as each package defines.

The design basis comes from the project’s own documents: the single line diagram and utility criteria, fault and insulation levels, statutory clearances, equipment GTP and drawings, soil information where earthing or foundations depend on it, and the master drawing list (MDL). Where an input is missing we say so, record the assumption we propose and ask the client to confirm it. Loads, levels and positions pass to civil and structural design as controlled interface data.

Inputs the design depends on

InputWhy it matters
Single line diagram, bay list, utility criteriaDefine the bus scheme, bays and ratings
Fault levels and insulation levelsDrive conductor, earthing and clearance design
Technical specification and MDLSet deliverables, formats and codes
Vendor GTP and drawingsFix dimensions, weights and terminal loads
Soil resistivity dataNeeded for the earth grid and foundations

Section 01

Electrical Engineering Drawings

Drawings first, beginning with the Single Line Diagram.

Drawings come first because they fix how the yard is arranged and connected. The Single Line Diagram (SLD) shows the bus scheme, bays, feeder and transformer connections and ratings. The Overall General Arrangement (GA) and the electrical layout plan and sections place the equipment on site so that bus levels and clearances can be checked. The Erection Key Diagram (EKD), in plan and section, identifies the equipment and fittings of each bay for erection; its content and format follow the client’s specification.

Protection, control and SCADA drawings are included only where the contract assigns them: protection and control schematics and SAS–SCADA interface drawings. Detailed vendor panel manufacturing drawings are not assumed to be prepared by CoreGrid.

Diagrams

  • Single Line Diagram (SLD), bus scheme and bay configuration
  • Protection and metering SLD, where in scope
  • LT AC and DC auxiliary system SLDs, with battery, charger and DCDB interface
  • Control and protection schematics / SAS–SCADA interface drawings, where part of the contract

Layouts

  • Overall General Arrangement (GA) / switchyard GA
  • Electrical layout plan and sections, bay elevations, equipment positions and electrical clearances
  • Erection Key Diagram (EKD): plan and section

Earthing, lightning, cables and lighting

  • Earth mat layout / earthing grid layout, with equipment earthing and bonding details
  • Direct Stroke Lightning Protection (DSLP) layout
  • Power and control cable routing layouts, cable trench layout, cable block diagram
  • Indoor and outdoor illumination layouts

Section 02

Electrical Design Calculations

Sizing and design checks. Transmission line sag–tension is a different calculation and sits on the transmission lines page.

Calculations are separate from drawings and from system studies. Conductors and busbars are selected for current, temperature and fault withstand. For flexible buses the sag–tension calculation fixes how the conductor hangs and what tension it passes to gantries and terminals. The short-circuit force (SCF) calculation is a mechanical, electrodynamic check on conductors, spacers, insulators and supports, and its results become loads for structure and foundation design. It is not the short-circuit (fault level) study, which is a network study listed under studies.

Earthing design starts from measured soil resistivity and the fault current and duration the grid must carry. We size conductors, calculate grid resistance, ground potential rise (GPR) and step and touch voltages against the project limits, and model non-uniform soil in SES-CDEGS where the project needs it. We do not promise a target resistance before the calculation is complete. DSLP is calculated by the project’s chosen method and then drawn as a layout.

Illustrative gantry elevation with flexible bus and load arrows
Loads from conductors, wind and short-circuit forces pass to gantries and foundations. Generic illustration.

Conductors and busbar

  • Conductor and busbar sizing / selection (current, thermal and short-circuit criteria)
  • Flexible / strung busbar sag–tension
  • Busbar short-circuit force (SCF) and critical span, mechanical support load check

Earthing and lightning

  • Earthing system / earth grid design: soil resistivity, conductor sizing, GPR, step and touch potential
  • Direct Stroke Lightning Protection (DSLP) calculation

Equipment and auxiliary systems

  • Equipment rating and selection; CT, VT / CVT burden and sizing
  • Neutral grounding resistor (NGR) sizing, where applicable
  • Station battery sizing (220 V / 48 V or specified) and battery charger sizing
  • Auxiliary LT AC/DC load calculation; auxiliary transformer, UPS and DG sizing where contracted

Cables, lighting and settings

  • Power and control cable sizing, voltage drop and short-circuit withstand
  • Indoor and outdoor illumination design calculation (DIALux evo)
  • Relay setting calculations / setting sheets, where contracted

Section 03

Power System & Protection Studies

Power system and protection studies answer questions about the network rather than about one piece of equipment. They are prepared or reviewed as each project commissions them, from the client’s system data, and each proposal states the basis. Relay setting sheets follow from the protection coordination study and are listed with the design calculations, so the two are not counted twice.

Power system & protection studies, with scope and software

  • Load flow / power flow study
  • Short-circuit / fault level study
  • Insulation coordination study
  • Harmonic analysis / harmonic load flow study
  • VFTO study for GIS, where appropriate
  • Switching transient / transient overvoltage study, where required
  • Protection coordination / selectivity study
  • Reactive power compensation / voltage regulation study
  • Grid interconnection study for renewable, pooling and BESS, as contracted

Section 04

Schedules, Quantities, Document Control & Technical Review

Schedules, quantities and document-control items support the drawings and calculations. They are listed apart from them and are never sold as drawings. The master drawing/deliverable list (MDL), bills of quantities, GTP and vendor drawing review sheets and the comment resolution sheet (CRS) belong here.

Schedules and lists

  • Power and control cable schedules and cable termination schedules
  • Equipment and load lists
  • Engineering design basis / criteria and interface documents
  • Calculation and drawing registers

Quantities, control and review

  • Master drawing / deliverable list (MDL)
  • Erection BOQ, overall BOQ and quantity take-off
  • GTP and vendor drawing review
  • Comment Resolution Sheet (CRS)

Open the electrical schedules and documents in the library

Electrical engineering by infrastructure type

InfrastructureElectrical focus
AIS/GIS substationsBus schemes, yard and hall layouts, SCF, earthing, DSLP, equipment ratings, auxiliary systems
Solar, wind and hybrid plantsPlant and collector SLDs, inverter and transformer interfaces, cable sizing, plant earthing, evacuation scheme
Pooling substationsCollector bay scheme, pooling transformers, GA and sections, Erection Key Diagram, metering, utility protection and SCADA interfaces
Battery energy storageMW/MWh sizing basis, PCS and transformer interfaces, eBoP SLD, auxiliaries, protection, EMS/SCADA interface
Transmission linesConductor selection, losses and corona, clearances, line entries into substations
HVDC stationsAC switchyard and filter yard layouts, converter transformer yard interfaces, station earthing

Share your SLD, technical specification or MDL for an engineering proposal

Send us the tender extract, single-line diagram, master deliverable list or the specific calculation you need. We will confirm scope, inputs and a realistic submission sequence before any work starts.