CoreGrid Engineering

Engineering service

Engineering Studies & Calculations

Earthing and lightning protection, short circuit, load flow, insulation coordination, harmonic and other studies that support substation, renewable, storage, line and HVDC design. Each study is offered on a stated basis.

Generic earth grid layout with potential contours
Earthing study output. Generic illustration.

Studies and their basis

“Prepared” means we carry out the study. “Prepared or reviewed” means either, depending on the contract. Where specialist or OEM input is needed, we say so in the proposal.

StudyQuestion it answersTypical inputsBasis
Earthing (GPR, step and touch)Is the earth grid safe for the specified fault?Soil resistivity, fault current and duration, layoutPrepared, including SES-CDEGS for complex soil
Direct stroke lightning protectionAre equipment and buses shielded?Layout, heights, shielding methodPrepared
Busbar short-circuit forces and sag-tensionWhat loads reach structures and terminals?Fault level, spans, conductor dataPrepared
Short-circuit studyWhat fault currents must equipment withstand?Grid data, network impedancesPrepared or reviewed, by scope
Load flow and reactive powerDo voltages, loading and reactive capability meet requirements?Network model, operating cases, capability dataPrepared or reviewed, by scope
Insulation coordinationAre arresters and withstand levels coordinated?System voltages, arrester and equipment dataPrepared or reviewed, by scope
Harmonic analysisAre distortion limits met; is a filter needed?Emission data, network impedance, limitsBy scope, with specialist input where needed
Neutral grounding resistor sizingWhat NGR rating does the reactor or transformer need?Fault current, duration, equipment dataPrepared
Battery, charger and cable sizingAre auxiliary systems adequate?Load lists, duty cycles, routesPrepared
IlluminationDo lighting levels meet the criteria?Lux criteria, photometric dataPrepared
Line conductor, losses and coronaWhich conductor suits the transfer and climate?Power transfer, voltage, climatic dataPrepared
HVDC converter-related studiesInsulation coordination, harmonics, control and protectionOEM design data, system dataReview and coordination with the OEM
Electromagnetic transient studiesSwitching and transient behaviourDetailed models and dataCase by case, confirmed at enquiry

How a study is carried out

Data

System and equipment data are collected from the client and suppliers, with gaps listed and assumptions agreed.

Model and cases

The model and the study cases are set out before results are produced, so the client can confirm the scenarios.

Results

Results are compared with the project’s acceptance limits, and any non-compliance is stated plainly.

Design decisions

Recommendations go back into the design: grid layout, equipment ratings, filters or settings inputs.

Tools

Studies are carried out with tools suited to the work, including SES-CDEGS for earthing, ETAP for power system studies and PSCAD for transient simulation where a study needs it. The client’s specification decides when a particular program or version is required.

Tools and standards

Share your SLD, technical specification or MDL for an engineering proposal

Send us the tender extract, single-line diagram, master deliverable list or the specific calculation you need. We will confirm scope, inputs and a realistic submission sequence before any work starts.